Thereafter, the performance bank guarantee was also submitted by the Adani, and
ultimately PNGRB issued the final authorization for Ahmedabad city and Dascroi area,
excluding the disputed areas. The Court noticed that the bid for the disputed area was
issued on 01.10.2015 and Adani participated in the bidding process, rather than
challenging it. The petition was filed only after it was unsuccessful in the bid. The High
Court found that the challenge to Regulation 18 of the CGD Regulations therefore, was
only when it suited Adani's convenience.
8. The impugned judgment then noted that this Court, in its judgment reported as In re
Special Reference No. 1 of 2001 MANU/SC/0267/2004 : (2004) 4 SCC 489 (hereafter
called "Special Reference"), had ruled that in view of Entry 53, List I of the Seventh
Schedule, the Parliament had exclusive legislative competence, and the Central
Government, exclusive executive competence on the subject of natural gas, and that
State Governments did not have any authority to enact such a legislation or to grant any
authorization in respect of the subject of natural gas. The High Court held that:
The Parliament has, therefore, made provision with regard to 'deemed
authorization' Under Section 16 of the PNGRB Act subject to the provisions of
Chapter IV which includes Section 17 of the PNGRB Act. If the provision
contained in Section 17 of the PNGRB Act is seen, it provides for distinction
between the entities authorized by the Central Government and those not so
authorized. Further, the entities authorized by the Central Government have to
furnish the particulars of their activities before the appointed day to the
Respondent Board, whereas, the other entities have to apply for authorization
Under Section 17(2) of the PNGRB Act and Regulation 18 of Regulations of
2008. Thus, the Parliament, while enacting Section 17(2) of the PNGRB Act, had
given a chance to such entities to apply for authorization to Respondent Board
in respect of the areas in which they were active before the appointed day. At
this stage, it is also required to be noted that the Petitioner No. 1 commenced
the work of CGD network in Ahmedabad District on the basis of the interim
policy of the Government of Gujarat. The said policy itself provides that as and
when the Gas Act or any other relevant Regulation is brought into force, the
Petitioner No. 1 will have to meet with the requirements of the Regulation.
Further, the NOC granted by the Government of Gujarat is also subject to
similar condition. In fact, the Presidential Reference was with regard to the
Gujarat Gas Act and ultimately the Hon'ble Supreme Court, in the case of
Association of Natural Gas and Ors. (supra), struck down the constitutional
validity of Gujarat Gas Act and held that with respect to natural gas, only the
Central Government has legislative competence. Thus, from the date of coming
into force of PNGRB Act i.e., on 01.10.2007, only the Central Government is
having legislative and executive competence and therefore Parliament
introduced 'deemed authorization' in Section 16 of the PNGRB Act. Therefore,
when the Parliament introduced the concept of 'deemed authorization' in
Section 16 of the PNGRB Act, it could only be with respect to entities operating
under an executive order/authorization from the Central Government. If Section
16 of PNGRB Act is interpreted to mean "deemed authorization" even to entities
operating without such executive order/authorization, such interpretation would
run contrary to the Presidential Reference answered by the Hon'ble Supreme
Court. As observed hereinabove, Section 16 of the PNGRB Act is subject to the
provisions of Chapter IV which includes Section 17.
12.1. If we consider the provisions contained in Sections 11, 18, 19 and 61 of
the PNGRB Act, it is clear that the Respondent Board has been empowered